Investments in progress or finished in 2021

Start of main content

Code Name of work Approved budget (euros) Initially approved amount (euros) Approved in year (euros) Situation
Investments in progress or finished in 2021
a) In new work projects:        
HU1A3004 Upgrading of the navigation channel to new traffic 358,033.00 279,359.48 127,928.74 In progress
HU1A13004 North expansion of the South Wharf 33,070,160.75 27,925,436.88 7,705,787.52 In progress
HU1E1005 Widening the access road to the South Wharf 7,074,711.00 4,947,345.86 1,206,922.02 In progress
HU1C3001 Multifunctional Building in the South Wharf and surrounding areas 5,073,595.57 1,704,505.99 1,698,243.88 In progress
HU1E9002 Reorganising access to the South Wharf 2,953,590.14 2,953,590.14 413,102.77 Finished
HU1E2006 Improvement of safety and layout in the network (WP 4.2) (II.SS. command and control for the Railway Network) 2,994,284.77 2,294,284.77 1,779,274.78 Finished
HU1B3006 Collecting water on the Juan Gonzalo and Ciudad de Palos Wharves 16,713,074.02 16,713,074.02 3,234,600.13 Finished
HU1D9001 Energy efficiency plan 512,523.88 292,954.07 71,231.42 In progress
HU1G2006 New Techniques for the management of dredged material (R&D) 113,400.00 113,400.00 32,400.00 Finished
HU1H2002 Soil characterisation 200,000.00 133,666.05 133,666.05 In progress
HU1H1011 Upgrading of Francisco Montenegro Avenue 9,386,990.14 9,386,990.14 4,245,596.50 Finished
HU1E9001 Measures to improve accessibility  109,250.00 109,250.00 109,250.00 Finished
HU1B4009 Upgrading of the Levante Wharf (partial demolition of the fish auction unit) 579,817.75 117,487.99 117,487.99 In progress
HU1H1005 Retrofitting to guarantee the structural stability of the Compañía Española de Minas de Tharsis loading dock 5,292,309.45 21,570.77 21,570.77 In progress
HU1G6001 Land acquisition 1,743,120.00 1,743,120.00 1,743,120.00 Finished
HU1H9010 Digitization of port processes 4,606,002.91 1,449,960.42 811,531.01 In progress
HU1I1003 Network and cybersecurity infrastructures 452,142.92 419,067.94 419,067.94 In progress
HU1I9001 Infrastructure compartmentalisation and digitalisation (2) 2,620,476.39 84,333.34 84,333.34 In progress
HU1G5005 IT equipment 72,883.41 72,883.41 72,883.41 Finished
HU1G2001 Technical assistance 552,423.10 552,423.10 552,423.10 Finished
HU1H9001 Other investments 3,654,743.31 3,654,743.31 3,654,743.31 Finished
HU1I1002 Applications and right of use 41,497.83 41,497.83 41,497.83 Finished
HU1G4002 Settlement  709,780.65 709,780.65 709,780.65 Finished
HU1H3001 1,5% cultural (2% after octuber 2021) 439,734.22 439,734.22 439,734.22 Finished
      Sum A) 29,426,177.38  
b) In conservation projects:        
  Draft maintenance dredging in inland waters of the Port of Huelva 9,469,981.77 8,805,417.47 2,172,076.49 In progress
  Restoring the Monument to the Faith of the Explorer 332,221.38 332,221.38 332,221.38 Finished
      Sum B) 2,504,297.87  
RESUME          
  a) Investments in new work projects     29,426,177.38  
  b) Investments in conservation projects     2,504,297.87  
TOTAL       31.930.475,25  