Description of the most important works

Start of main content

During 2019, Huelva Port Authority invested €20,5 million to refurbish its infrastructures to meet the existing needs.

The following key actions were completed this year:

Creating a forecourt for Ro-Ro freight intermodal traffic on the South Wharf

The work consisted of creating the forecourt to the south of the South Wharf as an area for vehicle and cargo RO-RO loading/unloading operations.

A surface area of 53,625 m2 was developed and paved, with two clear areas for storage or parking:

The paving is hot bituminous concrete-type compounds on a base of aggregate.

The development was completed with the infrastructures required for the planned use of this area: drainage, sanitation and supply facilities, lighting, communications and control. The enclosures, signage and beaconing were also carried out.

Repairing the Juan Carlos I breakwater after the 2018 storms.

  • Outdoor vehicle parking prior to the inspection checks with room for 75 lorries and 19 light vehicles.
  • Indoor vehicle parking with restricted access after the inspection checks, with room for 176 semi-trailers and 264 light vehicles.

Repairing the Juan Carlos I breakwater after the 2018 storms

As the result of Storm Emma, at the end of February and early March 2018, the whole infrastructure of the Juan Carlos I breakwater and surrounding area had to be repaired.

Therefore, the damage has been redressed by adding similar blocks to the existing cubic ones and with a volume of 4.62 cubic metres where blocks were lost and laying between 4,000 and 6,000 kg of rock fill, along with other action such as erecting wild animal fencing, access gates and facilities area, and replacing the artificial aggregate layer at the top of Complex 4..

Other actions started in 2018 and not completed during the year include:

New fish and seafood exporters’ warehouses

The building in question is at Avenida de Enlace no. 44, on the corner with Calle Alonso de Ojeda, on a plot of 15,117 m2. This building is part of the remodelling of a 65000- m2 space in the northern area of the Levante Wharf. On the one hand, this will help to readapt the old fisheries infrastructures on the Wharf, to resize them to current economic activity and, in turn, to open up the port area to the general public.

The building houses 41 modules for exporters, three empty premises and spaces for the agents operating in the zone, along with areas for the general public, with a bike lane connecting the venue to the city. In general, its ground floor is 6,485.96 m2 used for logistics, a first floor measuring 3,208.18 m2, a second floor of 183.62 m2 and a third floor with a built surface area of 98.90 m2, with a terrace available for users.

Collecting water on the Ingeniero Juan Gonzalo and Ciudad de Palos Wharves

The work consists of setting up a new rainwater drainage network on the Wharves, which prevents the rainwater flowing directly into the river estuary.

New manifolds with decanting stormwater drains, new surface paving to adapt it to the new slopes needed, and a large stormwater tank to regularise the water are being built.

In turn, new piping to supply raw water is also being installed to clean and flush the operations surface of the wharf and fibre optic and electricity piping will be restored.

Access and road reorganisation to the future logistics zone (ZAL) of Punta del Sebo Phase 1

The work consists of creating a new access route for heavy vehicles to the Punta del Sebo Industrial Estate from the H-30, which will allow the companies on the industrial estate and in the future logistics zone to be connected with the Outer Port and the Spanish General Highway Network.

This first phase involves the initial 600 metres from Calle Sabina Negral to the connection with the extension of the Calle Calderón de la Barca, inclusive. That work is on land that is available and regarding which there are no records of former activity being located there.

This new road, which will allow better access and greater mobility through the industry and port area, is a dual carriageway, with each side having two lanes, separated by a 1-m wide divider. There are 2.50 m wide parking spaces and 2-m wide pavements on both sides. Lighting, low and medium voltage, sanitation, utilities, telecommunications, traffic lights and sprinkling are also planned.

The most important actions that were started in 2019 and where work continues are:

Reorganising access on the South Wharf

The works consisted of reorganising and developing a 50,197 m2 port area, including the access road to the loading and to the future terminal, along with the prior inspection controls at the restricted loading area of the Maritime Terminal.

 The paving is designed with a road surface of hot bituminous concrete-type compounds, except for the area of the inspection controls prior to the restricted loading area which has concrete paving. The development was completed with the infrastructures required for the planned use of this area: drainage, sanitation and supply facilities, lighting, communications and control. The project also includes enclosures, signage and beaconing, and defining the control areas (concourses, control equipment, ancillary buildings).

Upgrading and widening the access road to the South Wharf

 The works consisted of upgrading the access road to the South Wharf between pk 0+000 and pk 3+640, along with the widening from pk 3+640 to pk 7+380 of that same road.

 The first section only requires the road surface to be treated, except in those sections where the platform is widened due to upgrading intersections. The second section requires the platform widened to a total width of 18 m so that there is room for 2 two-lane carriageways, with each having a central separation of 80 cm marked off by curbs and markers. The lanes will be 3.30 m to keep the speed low.

 On the other hand, a series of underpasses is planned to solve the intersection crossing in order to ensure that the road does not have any gauge limitations, along with strengthening the underpass at p.k. 4+328 for cranes and vehicles with special loads.

Finally, the power and telecommunications facilities were connected and the lighting is by means of 12m-high columns with LED lights.

Refurbishing the Avenida Francisco Montenegro

Avenida Francisco Montenegro is the main road that connects the city of Huelva and the inner port to the outer port. The avenue is nearly 5 km long and it is not currently suitable for pedestrians along its whole length.

 The work consists of refurbishing and developing this Avenue and the edge of the frontages of the adjoining plots in order to bring it into the city and for it to no longer be an industrial avenue.

 The refurbishing of Avenida Francisco Montenegro included the following actions:

  • Making a new two-metre reservation to be landscaped so the avenue better blends into the setting.
  • Removing the existing railway line (recovering and reusing the materials).
  • Laying pavements with the same surface paving to that on the righthand side of the avenue.
  • Concrete pavement milling and laying a new bearing layer with SMA 11, with low noise impact and proven durability.
  • Relaying the existing fibre cement pipes under the pavement to be demolished and rebuilt.
  • Creating parking places wherever possible, particularly in the area around the Huelva Yacht Club.
  • Refurbishing the timber walkway along the right side of the avenue according to the study at APH.
  • Detailed study of the power lines to ensure they have the necessary power for the designed facilities, which will include lighting that respects the type of lamps recently installed in the area.
  • Aesthetics and landscaping, creating gardening similar to the one to be found locally and "green screens" on the left side.
  • Landscaping slopes and green areas and creating recreational spaces.

North expansion of the South Wharf

The works consists of expanding the current South Wharf of the Port of Huelva along 526 m. The type of structure will be a screen wharf with a main screen anchored to an anchoring screen on the base slab. Both screens will be sheet piles.

The work initially envisages two different draught areas, one 10m draught (southern half) and another with 6m draught (northern half). However, the wharf design allows its draught to be adapted to the future needs of Huelva Port Authority up to a maximum of 17 metres draught.

The crest elevation of the wharf is the +6.50 m elevation (approximately, given that the surface has drainage slopes). The capping beam and the back guideway of the container cranes are made out of reinforced concrete and they function as pier cap beams of the sheet pilling. The back guideway of the gantry crane is also made out of reinforced concrete and is anchored on reinforced concrete pillars.

Furthermore, an area has been paved and it is 40.75 m wide including the capping beam and the guideways using 0.28m thick HP-40 reinforced concrete on a forecourt that is 1.00 m thick. The finish is then provisional with a 1.25m thick layer of quarry run.

Installing a perimeter security system. 2nd phase

In 2016, Huelva Port Authority instigated a prior assessment of its protection and security needs, which led to the tendering of works for the "Installation of a Perimeter Security System for the Port of Huelva. Phase 1", which were implemented during the first half of 2017, and which basically consisted of conveniently demarcating and protecting the perimeter and entrances of the Outer Port.

Phase 2 of the Perimeter Security Project was carried out in order to complete the installation and provide the perimeter demarcating the Outer Port Service Zone with a greater degree of protection. That involved installing a new fibre optic line, along with new protection and surveillance elements integrated with the existing ones.

Thus, the perimeter security of the port is approached from a converging, global and integral way; by fully integrating all the electronic and mechanical elements and systems, whose mission is to protect virtual, logical or physical perimeters to detect, stop and dissuade possible intrusion into their facilities.

Demolition of the former Shipyard premises

After terminating the contract for the current Shipyard facilities at the Port of Huelva, further actions are envisaged for the zone and some of the premises located on the Avenida de Enlace needed to be demolished.

The aim of the action was to demolish the Shipyard premises, including the dismantling of all the out-of-services premises, along with a perimeter enclosure.

Restoring the Monument to the Faith of the Explorer

The Monument to the Faith of the Explorer, located at the Punta del Sebo, is popularly known as the Monument to Columbus. It is a highly iconic monument in Huelva that is dedicated to the discovery of America.

In recent years, the monument has been damaged, mainly due to environmental and climate factors and the deterioration of its materials.

Most of the mountings need to be refurbished, several of the monument's lime blocks replaced and all its stone treated in order to guarantee an appropriate state of upkeep and maintenance of the monument.

Creating plant screens on the Ingeniero Juan Gonzalo, Ciudad de Palos and Minerales wharves

The northern area of the Ingeniero Juan Gonzalo Wharf, along with the Ciudad de Palos and Minerales wharves are used to stockpile bulk material. With the aim of improving the zone's environmental conditions and prevent the spread of dust and powder on windy days, a plant screen is going to be built to reinforce the irrigation system already on the wharves, to thus minimise even further the impact of that type of material on the surrounding areas.

The action consists of planting 1,700 large trees, setting up a sprinkling system and relocating and protecting a series of services that will be affected by the screen.

With respect to the projects drafted in 2019, in addition to those needed to implement some of the aforementioned investments, work has begun on preparing the following projects:

  • Cold piping network
  • New RO-RO ramp on the south wharf
  • Partial demolition of the fish auction house and of the Exporters modules on the Levante Wharf
  • Construction project to allow 550m long trains to operate in the Majarabique complex